This list describes the scale and scope of our major project construction division. This is not an exhaustive list as we routinely work on a multitude of projects. For an up-to-date resume, please contact our business development team.
Our Major Projects
Major Project #1
Diamond LNG – 1 Dawson Groundbirch Pipeline & Tie-In Project
PROJECT DETAILS:
- Designed and constructed two gas custody transfer and metering stations with bi directional flow capabilities
- Designed and constructed one gas pipeline blending facility equipped with metering
- 2 of 6 tie-ins used for this project. another tie-in was added in the 2024 project
- Designed and constructed gas analyzing stations
- Gas Chromatograph – Sales Gas Hydrocarbon Dew Point
- H2O Analyzer – Sales Gas H20 Dew Point
- H2S Analyzer – Sales Gas H2S Concentration
- Automated sites for 100% remote operations with control through client SCADA.
- Supply and install of cables
- Cable tray
- Grounding
- Junction boxes
- Yard lighting
- Electrical heat trace
- Instrumentation and tubing
- Transformers.
- Assisted with HVAC unit installation, Commissioning and Startup.
DURATION:
12 Months
APPROX
CONTRACT
VALUE
$2.5M-$5M
YEAR COMPLETED:
2022
Major Project #2
Kelt Farmington Battery
PROJECT DETAILS:
- Full battery build
- Office buildings
- Tank farm
- Inlets
- Dehy
- Compressors
- Fully Completed Site Automation
- Commissions to SCADA
- VRU
- Water Injection
- Transfer Pumps
- Turnkey MCC package
DURATION:
10 Months / Ongoing
APPROX
CONTRACT
VALUE
$5M-$10M
YEAR COMPLETED:
2025
Major Project #3
Keyera Kaps Power Solutions
PROJECT DETAILS:
- Full design build on a solar hybrid generator package for remote pipeline risers that required 480v power.
- Project was turnkey from design phase, to final product execution on site.
DURATION:
12 Months
APPROX
CONTRACT
VALUE
$2.5M-$5M
YEAR COMPLETED:
2023
Major Project #4
Pembina Namao PLC Migration
PROJECT DETAILS:
- Gas Plant PLC upgrade/migration.
- Various MOC jobs throughout facility.
DURATION:
6 Months
APPROX
CONTRACT
VALUE
$1.5M-$2.5M
YEAR COMPLETED:
2024
Major Project #5
Pure Life Heartland Project – Phase 1
PROJECT DETAILS:
- Power Distribution Design and Installation
- Lighting System Design and Installation
- Fire Alarm Design and Installation
- Lighting and Instrument Control Design and Installation
- Design and Installation to Canadian Food Safety Standard
- Fully Complete Site Automation
DURATION:
8 Months
APPROX
CONTRACT
VALUE
$2.5M-$5M
YEAR COMPLETED:
2020
Major Project #6
Inception Gold Creek Gas Plant
PROJECT DETAILS:
- New sales compressor install with fuel gas metering skid
- Pipeline sales metering skid
- PLC E-House
- New flare system
- 4 Compressors
- High & Low Pressure Inlets
- Treater
- Fully Completed Site Automation
- Commissioned to SCADA
- Generators
- Water Injection
- MCC
- VRU
- 6 Production Tanks
- I/A Skid
- Office
DURATION:
8 Months
APPROX
CONTRACT
VALUE
$5M-$10M
YEAR COMPLETED:
2018
Major Project #7
Pembina Becker Road Pump Station
PROJECT DETAILS:
- New custody transfer pump station
- New MCC building
- New pump buildings
DURATION:
6 Months
APPROX
CONTRACT
VALUE
$1M-$2M
YEAR COMPLETED:
2024
Major Project #8
Keyera – AEF to ADT iC8 Line Phase 1 & 2
PROJECT DETAILS:
- Install new cable tray, fittings, covers, and barriers.
- Demolition of existing equipment (ESDV’s, PSHH) and associated cables.
- Upgrading control panels with new modules and network switches.
- Installation of Variable Frequency Drive and associated motor control changes.
- Installation of a new UPS system and associated breakers & fiber optic communication parch panel accessories
DURATION:
3 Months
APPROX
CONTRACT
VALUE
$750k-$1.5M
YEAR COMPLETED:
2020
Major Project #9
Kelt Exploration Inga Lake 24 Well Pad Construction
PROJECT DETAILS:
- 24 Well Pad Construction
- Build and Install Wet Meter Skid on each well
- Install Two Group Separators
- Two Test Separators
- MCC Building
- Flare Knock Out System
- Fully Completed Site Automation
- Commissioned to SCADA
DURATION:
3 Months
APPROX
CONTRACT
VALUE
$1.5M-$2.5M
YEAR COMPLETED:
2019
Major Project #10
Kelt Oak Battery
PROJECT DETAILS:
- Full battery build
- Tank farm
- Compression
- Dehy
- Pump skid
- VRU
- Generators
- Turnkey MCC package
- Instrument air package
- Group and test seps
- Additional 4 wells on battery
- Fully Completed Site Automation
- Commissioned to SCADA
DURATION:
10 Months
APPROX
CONTRACT
VALUE
$5M-$10M
YEAR COMPLETED:
2022